Completed Projects BACK

Sl. No Name of work & Agreement No Date
of Start
Date of
Completion
Reasons for delay & compensation levied, if any Tendered Cost in Lacs Gross cost of completion In Lace Net amount Received Name, designation & complete address of the authority for whom the work was done
      Stipulated Actual          
1

Electrification of Plant Phase II nd expansion at Hardwar P.O No 3600004610 dt 25/08/11

Oct-11 Mar-12 Apr-12


 
Incrrease in volume of work 82
 
102   G.M CommercialKirbhy Buildings Systems India Ltd, Sidcul Industrial Area, Hardwar Contact Person Mr Pankaj Aggarwal
2 Conctriction Power,11 KV sub station & Power Distribution of Power Plant At Doosar , Rajasthan Aug-11 May-12 May-12 On Schedule 90 91   G.M Electrical ,Rajasthan Sun Technique Energy Pvt Ltd, Village Doosar, Pokhran, Rajasthan. Contact Person Mr S.K. Dubey.
3 11 K.V H.T Installation ,Electrification of plant, Cables, earthing, L.T Panels Agreement No A Oct-11 Feb-12 Feb-12 On Schedule 110 123   Factory Manager ,Apache Footwear India (P) Ltd.,Stiching DivisionMain Road, UPSIDC, Industrial Area, Selaqui. Contact Person Mr Morgan Chang.
4 Internal Electrification of Housing At Rosa Agreement No N Aug-09 Mar-11 Dec-11 Increase in volume of work 290 395   Chief Construction Manager,Utility Energy Tech & Enggrs Pvt Ltd, Rosa. U.P Contact Person Mr Mohanty
5 11 K.V Construction Power Work at Samallot Agreement No Jan-11 Mar-11 May-11 Increase in volume of work &non clearance of site 80 395   D.G M Electrical, Rekiance Infra Ltd, Samalkot,Andhra Pradesh Contact Person Mr Surya Murthy
6 Office electrification, secuirty system, Lain wiring Of Surya Kiran Building Agrrement No Ser/DSA/23522033 dated 23/05/10 Aug-10 Sep-11 Mar-11 Increase in scope of Work &non completion of interior work 90 135   Generlal Manager, BSES Yamuna Power Ktd, New Shakti Nagar Building ,KarkarDoma, Delhi
7 Supply/Erection of 33/11 KV Substation,Streetlight, & Cabling work at Patanjali Ayurvedic Ltd, Padartha, Hardwar Agreement No ; Pal/09/1555 dated 14/01/09 Jan-09 Oct-10 Apr-11 Enclusion of additional internal plant distribution cabling work 310 406   Patanjali Ayurvedic Ltd. , G.M Electrical, Village Padaratha, Hardwar, Uttarakhand, Contact Person, Mr Suresh Chiller
8 SITC of 11 K.V Substation , Panels, cabling & Earthing work in Plant at Selaqui Dehra Doon Po No 9000047-02 dated 24/09/09 Sep-09 Fab-10 Mar-10   117 147   General Manager Projects,Tupperware India Ltd., Central Hope Town, Industrial Area , Selqui. Contact Person Mr Raghunath
9 SITC of 11 K.V Substation , Panels, cabling & Earthing work in Plant at Selaqui Dehra Doon Po No Elec/Ext09 dated 12/07/09 Jul-09 Mar-10 Jun-10   139 157   Factory Manager ,Apache Footwear India (P) Ltd., Twin Industrial Area, Selaqui. Contact Person Mr Morgan Chang.
10 SITC of 11 K.V Substation , Panels, cabling & Earthing work at Phase Iind, Delhi Hardwar High way, Bhadarabad, Hardwar Po.No LOI dated 30/1/09 Jan-09 Mar-10 1-Dec Increase in volume of work 172 263   Patanjali Yogpeeth Trust Phase-II, Delhi Hardwar Highway, Bhadarbad, Hardwar Contact person Mr Chauhan.
11 Supply & Installation of 1000KVA transformer. Street lightings. External Cablings. Feeder pillars & internal wiring P.O No RPL/DD/06-07 dated 14/08/06 Aug-06 Jan-08 Jul.09 Increase in volume of work 162 192   Factory Manager, M/S Rusan Pharma Ltd , Twin Industrial Area, Selaqui ,Dehra Doon, Contact Person Dr Phuskar
12 Supply &Installation of 1000KVA transformer,Paneling, Cable Tray & Earthing work at Dehra Doon Plant. P.O No BEL/HYD/2007-08 dated 13/06/07 Jun-07 Aug-07 Aug-07   108 127   General Manager, Biological E Ltd. Pharma City, Selaqui, Dehra Doon. Contact Person Mr R.K. Jha
13 Supply & Installation of 2000KVA transformer. Street lightings. External Cablings. Feeder pillars & internal wiring P.o No GMI/132 dated 15/10/08 Oct-08 June-09 Sep-09   174 195   General Manager, Global Medi Kit Ltd. Central Hope Town, Selaqui, Dehra Doon. Contact Person Mr Munish Sharma

 

 
 
     
 